The worst building in Moscow began to take down

43

Photo: Anton Denisov/ RIA Novosti

In Moscow began the demolition of the unfinished Hovrinskaya hospital. About it reports “Interfax” with reference to the Moscow Department of construction.

According to the original plan, demolition of the Hovrinskaya hospital was supposed to start in November 2018 and be completed in February 2019. Workers started dismantling ahead of schedule due to the high importance of the spare areas for a restoration programme in Khovrino district.

“The winner of the competition to determine the contractor’s demolition work requested ensure early access to the site. This decision was agreed, whereby the contractor was given access to the site from today”, — quotes the message of Department of construction, “Interfax”.

The competition for the contract for the demolition of the unfinished was won by OOO “Stroyekoresurs”. The starting price of the contract was in the order of 919 million rubles, the winner of the tender offered to carry out the demolition at 381,4 million.

In place of the demolished buildings is planned to build four houses with a total area of 315 thousand square meters. Apartments in these complexes will be provided to immigrants under the program of renovation.

The construction of the Hovrinskaya hospital was started in 1980-e years, already in 1985 work was suspended. In 1992, the construction was completely frozen. Currently, the building is unfinished, is in critical condition, his basement flooded. The hospital is considered dangerous because of the destruction and allure of abandoned buildings for the marginalized. The building is surrounded by numerous urban legends about him as the film in the horror genre.