Unfinished metro in Omsk, will pour cement

725

www.vsyako.netPhoto: Dmitry Feoktistov / TASS

The plot of the unfinished metro in Omsk between stations “working” and “Marshal Zhukov” is filled cement-sandy solution. About it reports “NGS Omsk”.

“View preservation of the right-Bank section of the first metro line (station “Library of a name of A. S. Pushkin”) and starting area (the station “Zarechnaya” and “Crystal”) will not be changed: in these areas will be carried out “dry” conservation”, — quotes the edition of the Deputy Minister of industry, transport and technology innovation in the region Igor Lukyanov.

The decision to change the method of conservation with the “dry” to “wet” adopted by the government of the region in order to save. According to the portal “City of 55”, the work will cost 10.8 million rubles.

Under “dry” conservation means the completion with pre-existing structures, equipment, systems of ventilation, lighting and sanitation. This will keep the objects until the moment is resolved to use them.

In February it was reported that the authorities of Omsk have decided to completely stop the construction of the metro started 27 years ago, to preserve the project and to recognize it as inappropriate because of lack of money for its implementation. The decision was taken after consultation with the Federal authorities.